Construction scheduling software: free plans and trials

Free construction scheduling software, sorted by what's free: desktop programs, free plans and their limits, and trials. Plus when a GC needs full CPM.

UpdatedNov 24, 2026
First publishedNov 24, 2026
Tools on this pageMicrosoft Project, Primavera P6, Asta Powerproject +5

The short answer

Few construction schedulers are free to keep. ProjectLibre Desktop and GanttProject are free desktop programs, and Fieldwire's Basic plan is free for up to 5 users, 3 projects and 100 sheets, though Fieldwire says it has no native critical-path scheduling. Most construction tools offer a trial instead: Contractor Foreman for 30 days, Asta Powerproject for 14 days, Microsoft Planner Plan 1 for a month, and Outbuild and Touchplan for an unstated length. Primavera P6 lists no free plan or trial.

Which construction scheduling software is free?

Construction scheduling software comes free in three ways: a free desktop program, a free plan with limits on users and projects, or a trial that ends. Most of the tools contractors use for CPM scheduling are in the third group, and Primavera P6 isn’t in any of them.

Tool What’s free Limits or terms Paid price Scheduling method
ProjectLibre Desktop Free, open-source desktop app Single user; Windows, macOS, Linux Cloud from $9.99 per user a month, billed annually Critical path, network diagram
GanttProject Free desktop app Offline; Windows, macOS, Linux None Gantt; critical path not mentioned
Fieldwire Basic plan, $0 5 users, 3 projects, 100 sheets Pro $39 per user a month, billed annually Tasks and look-ahead; no native CPM
Microsoft Project Planner Plan 1, one month free Timeline (Gantt) view Plan 3 $30 per user a month Critical path on Plan 3 only
Contractor Foreman 30-day free trial Full trial, then annual or monthly plan From $49 a month billed annually Gantt with CPM
Asta Powerproject 14-day trial download Windows desktop Quote Construction planning, 4D BIM
Outbuild Free trial Length not stated From $999 a month billed annually Imports P6, exports XER
Touchplan Free trial Terms not stated Quote Pull planning
Primavera P6 Nothing stated Contact form and demo only Quote CPM; the XER format owners ask for

Prices are from vendor pages read in November 2026.

Free desktop programs: ProjectLibre and GanttProject

ProjectLibre Desktop is the closest thing to a free Microsoft Project. ProjectLibre describes it as free and open source with no subscription, and lists Gantt charts, WBS, network diagrams, critical path, resources, costs, baselines and earned value. It opens Microsoft Project files and says it can import Primavera P6 files too. The limit is in its own description: Desktop is for a single user on individual projects, and team features live in ProjectLibre Cloud, which starts at $9.99 per user a month billed annually.

GanttProject is free, runs offline on Windows, macOS and Linux, reads MPP, MPX and XML files from Microsoft Project, and exports to Microsoft’s XML format. Its site lists resource allocation but doesn’t mention critical path, so if you need float and a driving path, try ProjectLibre first.

Both are free construction scheduling programs in the sense that they cost nothing, and neither is built for construction. There are no trades, no field app and no RFIs, and the schedule lives in a file on one person’s laptop.

Free plans and trials from construction vendors

Fieldwire is the only construction platform on this list with a free plan you can keep, and it’s built for the field more than the scheduler. Basic is $0 for up to 5 users, 3 projects and 100 sheets. Fieldwire’s own comparison page says it has no native critical-path scheduling, handles task sequencing and short-term look-ahead planning, and that teams needing Gantt-based schedule management run a separate tool alongside it. Use it for look-ahead planning and punch work, and keep the baseline somewhere else.

Contractor Foreman gives a 30-day free trial and then charges from $49 a month for one user on annual billing, or $139 a month monthly for up to 3 users. Its scheduling page says you can build or import Gantt charts, use CPM to see which tasks drive the completion date, compare baselines with actual progress, and import from or export to Microsoft Project. The page also says features vary by tier and doesn’t say which plan includes the scheduler, so confirm that during the trial.

Microsoft splits the features across plans. Planner Plan 1 is one month free, then $10 per user a month paid yearly, and gives you a timeline (Gantt) view. Baselines, critical path, lead and lag dependencies and the Project desktop app come with Planner and Project Plan 3 at $30 per user a month, which offers a free trial without saying how long. Project Online, the old cloud service, retired on September 30, 2026; the desktop app carries on.

Asta Powerproject offers a 14-day trial download for Windows, with 4D BIM and resource management, and sells single-user, concurrent and SaaS licenses by quote. Outbuild and Touchplan both offer free trials without stating the length. Outbuild imports from Microsoft Project or P6, exports PDF, XML or XER, and starts at $999 a month billed annually with unlimited users. Touchplan is free construction planning software only for the trial; it’s built for collaborative pull planning, and its BoardScan AI turns photos of Big Room planning boards into digital tickets at no extra charge.

When a free Gantt chart stops being enough

You outgrow a free Gantt tool when someone else starts setting the rules for your schedule: an owner’s spec, a lender’s draw schedule, or a claim you have to defend. A CPM schedule adds logic links between activities, float, and a critical path you can point to when a delay hits, and owners’ specs and delay claims are written around those.

Government specs spell this out. The Army Corps of Engineers’ standard Project Schedule section, UFGS 01 32 01.00 10, requires every project schedule to use the Critical Path Method with the Precedence Diagram Method, and caps non-procurement activities at 20 workdays or 30 calendar days. It says the Government uses Primavera P6 and wants schedules as XER exports in a P6 version the Government can import. It also requires software that is commercially available with vendor support agreements, which a free open-source desktop app may not meet. If you pick something other than P6, you supply two licenses, two computers and training for two Government employees. Private owners’ specs vary, so read the schedule section in Division 01 of your contract before you choose.

Other signs you’ve outgrown it:

  • More than one person has to edit the schedule, and a single-user desktop file keeps getting emailed around.
  • The owner wants monthly updates with a narrative, and you need baselines to show what moved.
  • You’re writing a delay notice or time-impact analysis and need the logic to hold up.
  • Subs need to see their look-ahead on a phone, which a desktop file can’t give them.

What the paid step up costs

For CPM, the published prices start with Microsoft’s Plan 3 at $30 per user a month and Contractor Foreman’s plans, which bundle a CPM-capable Gantt with estimates and financials. Outbuild starts at $999 a month billed annually for unlimited users and exports the XER files owners ask for. Asta and P6 are quote-only, and P6 remains the format the rest of the market reads.

If your question is whether the schedule will hold, schedule analytics sit on top of whichever tool you use. SmartPM reads P6, Microsoft Project and Asta files, offers a 60-day risk-free trial, and charges $12,000 a year for its Essentials plan covering up to 50 projects. nPlan and ALICE publish no prices, and ALICE says its customers generally use it on projects of at least $75M. For a full comparison of paid schedulers, see the construction scheduling software guide.

Questions people ask

Is there free construction scheduling software?

Yes, two kinds. ProjectLibre Desktop is free and open source, runs on Windows, macOS and Linux, and calculates the critical path, but it's built for a single user. Fieldwire's Basic plan is free for 5 users and 3 projects and handles tasks and short-term look-ahead planning, with no native critical path.

Does Microsoft Project have a free version?

No. Microsoft offers Planner Plan 1 free for one month, then $10 per user per month paid yearly, and it has a timeline (Gantt) view but no critical path. Critical path, baselines and the Project desktop app come with Planner and Project Plan 3 at $30 per user per month, which has a free trial of unstated length. The one-time Project Standard 2024 license is $679.99.

Is there a free version of Primavera P6?

Oracle's P6 page lists no free plan or trial, only a contact form and a demo request, and no published price. If you only need to open a P6 file someone sent you, ProjectLibre says its free desktop app can import Primavera P6 files along with Microsoft Project.

What is the best free construction planning software for a small contractor?

It depends on who's building the schedule. A small GC running a handful of jobs can use Contractor Foreman's 30-day trial, which includes a Gantt scheduler with critical path, and then pay from $49 a month billed annually. A single scheduler who only needs a CPM file can use ProjectLibre Desktop for free.

Can I use free scheduling software on a government construction job?

Check the schedule section of your contract first. The Army Corps of Engineers' standard schedule spec requires software that is commercially available with vendor support agreements, says the Government uses Primavera P6, and asks a contractor on other software to supply two licenses, two computers and training for two Government employees.

Sources

Outside pages this article relies on. Vendor prices and plan details come from each tool's profile, where every figure links to the vendor page it came from.

  1. projectlibre.com/projectlibre-desktop
  2. projectlibre.com
  3. ganttproject.biz
  4. fieldwire.com/blog/procore-competitors
  5. contractorforeman.com/features/project-management/scheduling
  6. wbdg.org/FFC/DOD/UFGS/UFGS%2001%2032%2001.00%2010.pdf